Skip to main content
Money

Construction holdbacks in Ontario, explained

Ten percent of every payment you receive is money you cannot spend yet. If you price and schedule as though you can, the holdback quietly eats the margin. Here is how it actually works.

Ontario law
What it is

Ten percent, held by whoever is paying

Ontario's Construction Act requires anyone paying for construction work — the owner paying you, or you paying your subcontractors — to hold back 10% of the value of work certified on each payment. It is not optional and it is not something a contract can negotiate away. The statutory holdback exists to protect the subcontractors and suppliers further down the chain, who can register a lien against the property if they go unpaid.

Construction Act, R.S.O. 1990, c. C.30, s. 22

When it comes back

After the certificate is published and the lien period runs out

The basic holdback becomes payable after substantial performance of the contract is certified and published, and the lien preservation period that follows expires with no liens preserved. In sequence: the certificate is published, a 60 day window runs, and the holdback is released. On long contracts, annual or phased release can apply where the contract provides for it.

Construction Act ss. 26, 31, 32 — certification and publication of substantial performance; expiry of liens; payment of holdback

Worked example

For example, on a $600,000.00 contract, $60,000.00 of your revenue sits on a statutory timer you do not control, arriving months after the work is finished. The figures are illustrative arithmetic on a round number, not a claim about any real project.

Prompt payment

The clock starts at a proper invoice

Under the prompt-payment rules the schedule is defined by the proper invoice: an owner has 28 days to pay after receiving one, and a contractor who is paid must pay its subcontractors within 7 days. A dispute has to be raised by notice of non-payment and may go to adjudication — silence is no longer a payment strategy. Your invoicing discipline, meaning dates, contents and delivery, is now the difference between predictable cashflow and an unenforceable pile of receivables.

Construction Act Part I.1 (prompt payment, ss. 6.1–6.9); Part II.1 (construction dispute interim adjudication)

Consequences

What this means for how you run projects

  • Track holdback as its own number, per project — not buried inside accounts receivable. You need to know what is retained, by whom, and which date starts its release clock.
  • Model cashflow with the ten percent out , so a profitable project does not go cash-negative in month four.
  • Certify substantial performance promptly. Every week the certificate is not published is a week added to the statutory timer on your money.
  • Mirror the obligation downward. You hold back from your subcontractors the way the owner holds back from you, and release on the same statutory schedule.
In JobSite

What the software does with this

The holdback is a modelled obligation with a type, a percentage, an amount, a release trigger and a trigger date. JobSite records the release trigger and its date rather than promising to schedule anything on your behalf, and holds and releases post as double-entry movements against a segregated holdback account. Those are statements about the data model — see how it is built.

This guide is general information about Ontario's construction payment regime, not legal advice. Timelines and obligations depend on your contracts — confirm specifics with a construction lawyer.